Installation works in a Drainage Services Department temporary pumping station at CUHK


We carry out the installation works in a Drainage Services Department temporary pumping station at Chinese University of Hong Kong. This is a Design and Build project, which requires to install 3 sets of 75KW pump, and provide standby power supply, pump starter panel, and signaling system.

1. Build a new transformer room for CLP to install a new transformer to provide power supply.
2. Provide 2 pumps for normal operation, and 1 standby pump.
3. Provide 350KVA standby generator to provide the emergency power supply, for suspension of permanent power supply or during shut down of equipment.
4. Provide Programmable Logic Control (PLC), and also standby starter panel to start the pump when PLC is shut down or fault.
5. Provide 24 hours signaling surveillance system through mobile phone SMS to transmit the operation information to the maintenance staff.